Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by simon

Page: 26 / 127

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2024 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1702 Q&A's Shared By: simon
Question 104

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Discussion
Question 105

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Discussion
Question 106

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Discussion
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 2, 2024
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Aug 31, 2024
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Question 107

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Discussion
Page: 26 / 127
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599