Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by simon

Page: 26 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: simon
Question 104

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

Options:

A.

Avoid the conflict as the customer feels comfortable with using processes fromcompany A.

B.

Review the historical information and make the decision based on the return oninvestment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with theseprocesses.

D.

Work with the team to analyze which processes are suitable to use and define them inthe ground rules.

Discussion
Question 105

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Discussion
Question 106

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Discussion
Question 107

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Dec 3, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Dec 5, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Dec 5, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Dec 3, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Page: 26 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599