Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by corey

Page: 40 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: corey
Question 160

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Discussion
Question 161

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Questions 161

Options:

Discussion
Question 162

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

Options:

A.

Request a change in the contract to include the shipment in the project managementplan.

B.

Find the root cause of the issue and discuss the customer's current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Discussion
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Jan 17, 2026
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Jan 4, 2026
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Jan 14, 2026
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Joey
I highly recommend Cramkey Dumps to anyone preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Dexter Jan 6, 2026
Agreed. It's definitely worth checking out if you're looking for a comprehensive and reliable study resource.
Question 163

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Discussion
Page: 40 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599