Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMP Exam Questions and Answers by corey

Page: 40 / 148

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1988 Q&A's Shared By: corey
Question 160

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

Options:

A.

Included lessons learned from past projects

B.

Used bottom-up estimating

C.

Utilized three-point estimates

D.

Validated the schedule performance index (SPI) to evaluate deviation

Discussion
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Jul 13, 2025
Great. Yes they are really effective
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Jul 27, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jul 4, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Vienna
I highly recommend them. They are offering exact questions that we need to prepare our exam.
Jensen Jul 4, 2025
That's great. I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Question 161

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

Options:

A.

Modify the project management plan and get approval from relevant stakeholders

B.

Add more resources to recover the schedule without making changes to the baseline.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Negotiate with the project sponsor immediately and establish a new project charter.

Discussion
Question 162

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.

The product owner does not have visibility into what the team has done in the product increment.

B.

The product owner trusts the team and is marking the product as complete.

C.

The product owner has evaluated the product against the definition of done (DoD).

D.

The product owner will release the product to customers without showing them a demo.

Discussion
Question 163

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.

In the initiation process, as it happens concurrently with the project contract and project charter creation

Discussion
Page: 40 / 148
Title
Questions
Posted

PMP
PDF

$159.6  $399

PMP Testing Engine

$179.6  $449

PMP PDF + Testing Engine

$239.6  $599