Question 52

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

Options:

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Nov 19, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Nov 20, 2025
YES….. I saw the same questions in the exam.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Nov 15, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Nov 9, 2025
Yeah, definitely. I experienced the same.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Nov 4, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Question 53

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Discussion
Question 54

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.

Add the competitor's functionalities to the product backlog to improve the product

B.

Ask the sponsor to add more people to the team

C.

Help the team to find a new approach to launch the product as soon as possible

D.

Ask the team to increase the velocity to launch the product as soon as possible

Discussion
Question 55

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Discussion