New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by nolan

Page: 13 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: nolan
Question 52

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

Options:

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Discussion
Question 53

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Discussion
Question 54

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

Options:

A.

Add the competitor's functionalities to the product backlog to improve the product

B.

Ask the sponsor to add more people to the team

C.

Help the team to find a new approach to launch the product as soon as possible

D.

Ask the team to increase the velocity to launch the product as soon as possible

Discussion
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Nov 2, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Nov 11, 2025
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Nov 25, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Nov 9, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Nov 15, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 55

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Discussion
Page: 13 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599