Question 40

|

A project team is developing a product with monthly deliverables. The user feedback collected after each iteration affects how the product is developed further.

How should the project manager process the changes?

Options:

A.

Assign the changes to the development team based on the feedback received.

B.

Seek approval from the change control board (CCB) for the changes identified.

C.

Analyze the impact on the schedule and cost due to the changes identified.

D.

Incorporate the feedback into the backlog and work with the product owner for prioritization.

Discussion
Question 41

Recently, the company ' s leadership team attended a management conference where they discussed project management approaches. The leadership team has

tasked the software project team with using an adaptive approach on the current project. The project manager anticipates the team will struggle to adapt to this

approach in the next 3-month.

What should the project manager do next?

Options:

A.

Gather the team ' s feedback on the new policy.

B.

Evaluate the readiness and maturity of the team.

C.

Advise the team to take agile methodology training.

D.

Schedule daily coordination meetings with the team.

Discussion
Question 42

A team is working on a hospital construction project and is using a predictive approach. The team has encountered a challenge affecting their deadline because a

critical team member is on medical leave. The project is in jeopardy of falling behind schedule.

What should the project manager do first?

Options:

A.

Ask the functional manager to find a replacement team member.

B.

Discuss a schedule extension with the project sponsor.

C.

Assign all outstanding tasks to a team member who has capacity for work.

D.

Meet with the team to determine how the tasks can be reassigned.

Discussion
Question 43

A team is using a predictive model to determine possible cost overrun scenarios for a disruptive technology project. The data being used is pooled from various

projects implemented within the organization.

What should the project manager do to increase accuracy?

Options:

A.

Ensure that the data pool is broadened to include public domain projects.

B.

Ensure that the data pool consists of projects still in progress or not completed.

C.

Ensure the data pool consists of successful projects completed one year ago.

D.

Ensure the data pool is composed of projects with similar parameters.

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jul 11, 2026
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Jul 5, 2026
That makes sense. What makes Cramkey Dumps different from other study materials?
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Jul 28, 2026
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Jul 26, 2026
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.