Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by tamara

Page: 12 / 140

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1877 Q&A's Shared By: tamara
Question 48

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.

Start the project and add any uncertainty that arises to the risk register.

B.

Dissolve the virtual team and build a colocated team.

C.

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.

Build a culturally neutral team that will not be affected by cultural differences.

Discussion
Question 49

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Discussion
Question 50

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

Options:

A.

Decrease the scope of the portfolio and send new solutions to the customer.

B.

Deliver a schedule with the portfolio timeline and delivery to the customer.

C.

Adopt an incremental cycle of delivering value to the customer.

D.

Prepare deliveries with more details to satisfy the customer.

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Jul 17, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Jul 4, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Jul 24, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Jul 24, 2025
Thanks for the recommendation! I'll check it out.
Question 51

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

Options:

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Discussion
Page: 12 / 140
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599