New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by daniella

Page: 11 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: daniella
Question 44

A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.

What should the project manager do next?

Options:

A.

Make a change request regarding the project's scope to ensure compliance.

B.

Include an assessment to verfy compliance in the next iteration

C.

Conduct an iteration review to address the new regulation

D.

Start the tests over, adapting the trials to the new regulation

Discussion
Question 45

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?

Options:

A.

A release burndown chart

B.

Analysis of the business requirements document

C.

Story points for the remaining user stories

D.

Surrogate measurements

Discussion
Question 46

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

Options:

A.

Prepare the lessons learned from the project phase.

B.

Obtain official approval on the new process from the various countries

C.

Send a questionnaire to the project participants and seek their feedback.

D.

Refer to the communications management plan

E.

Deliver the project materials to the users and see if they have any comments

Discussion
Question 47

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

Options:

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Discussion
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Nov 19, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Nov 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Nov 21, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Nov 27, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Page: 11 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599