| Exam Name: | Project Management Professional (2025 Version) | ||
| Exam Code: | PMP Dumps | ||
| Vendor: | PMI | Certification: | Project-Management-Professional | 
| Questions: | 2040 Q&A's | Shared By: | daniella | 
A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?