Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by angelina

Page: 3 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: angelina
Question 12

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

Options:

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Discussion
Question 13

A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ask for expedited delivery of the component to mitigate the risk of schedule delays

B.

Ensure that relevant stakeholders and expectations are identified and assess the component delay

C.

Perform a detailed analysis of the release content for each component of the solution.

D.

Propose a new design of the solution to replace the external component with an internal one

Discussion
Question 14

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Discussion
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Dec 28, 2025
That's great. I think I'll give Cramkey Dumps a try.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Dec 20, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Dec 6, 2025
Thanks for the recommendation! I'll check it out.
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 15

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

Options:

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Discussion
Page: 3 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599