Question 28

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

Options:

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

Discussion
Question 29

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

Options:

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Nov 12, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Nov 7, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Nov 21, 2025
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Nov 3, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Nov 14, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Question 30

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?

Options:

A.

Make the decision on behalf of the organization

B.

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision

C.

Schedule a project decision meeting with all stakeholders to discuss the decision.

D.

Follow the stakeholder engagement plan

Discussion
Question 31

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

Questions 31

Options:

Discussion
Page: 7 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599