PMI Scheduling Professional
Last Update May 5, 2024
Total Questions : 323
To help you prepare for the PMI-SP PMI exam, we are offering free PMI-SP PMI exam questions. All you need to do is sign up, provide your details, and prepare with the free PMI-SP practice questions. Once you have done that, you will have access to the entire pool of PMI Scheduling Professional PMI-SP test questions which will help you better prepare for the exam. Additionally, you can also find a range of PMI Scheduling Professional resources online to help you better understand the topics covered on the exam, such as PMI Scheduling Professional PMI-SP video tutorials, blogs, study guides, and more. Additionally, you can also practice with realistic PMI PMI-SP exam simulations and get feedback on your progress. Finally, you can also share your progress with friends and family and get encouragement and support from them.
You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?
John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?