PMI Updated PMI-SP Exam Questions and Answers by zaynah

Page: 11 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: zaynah
Question 44

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

Options:

A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent (not set)
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Erik
Hey, I have passed my exam using Cramkey Dumps?
Freyja (not set)
Really, what are they? All come in your pool? Please give me more details, I am going to have access their subscription. Please brother, give me more details.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja (not set)
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson (not set)
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Question 45

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

Options:

A.

Perform resource leveling for the project.

B.

Crash the project schedule.

C.

Fast track the project.

D.

Remove things from the project scope.

Discussion
Question 46

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

Options:

A.

Work performance information

B.

Change requests

C.

Work performance measurements

D.

Forecasting method

Discussion
Question 47

You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

Options:

A.

Templates

B.

Rolling wave planning

C.

Decomposition

D.

Expert judgment

Discussion