Question 24

In which of the following process groups does Integration Change Control Process fall?

Options:

A.

Execution

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Oct 27, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Oct 16, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Everleigh
I must say that they are updated regularly to reflect the latest exam content, so you can be sure that you are getting the most accurate information. Plus, they are easy to use and understand, so even new students can benefit from them.
Huxley Oct 10, 2025
That's great to know. So, you think new students should buy these dumps?
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Oct 21, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Oct 19, 2025
Thanks for the recommendation! I'll check it out.
Question 25

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

Options:

A.

(O+ML+P)

B.

(O+(6M)+P)6

C.

(O+ML+P)/3

D.

(O+(4M)+P)/6

Discussion
Question 26

You are the project manager of the NHG. The following figure represents your project network diagram.

Questions 26

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Discussion
Question 27

You are the project manager for your company. You are working with the activities defined in the figure below.

Questions 27

What will happen to your project if Activity F takes five additional days to complete than what was expected?

Options:

A.

Your project's critical path will shift to ACFI.

B.

Your project will be late by five days.

C.

Your project can still complete on time as float is available on Activity I.

D.

Your project will now have two critical paths.

Discussion