Question 24

In which of the following process groups does Integration Change Control Process fall?

Options:

A.

Execution

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Discussion
Question 25

You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?

Options:

A.

(O+ML+P)

B.

(O+(6M)+P)6

C.

(O+ML+P)/3

D.

(O+(4M)+P)/6

Discussion
Question 26

You are the project manager of the NHG. The following figure represents your project network diagram.

Questions 26

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Discussion
Inaaya
Are these Dumps worth buying?
Fraser Dec 3, 2025
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Josephine
I want to ask about their study material and Customer support? Can anybody guide me?
Zayd Dec 4, 2025
Yes, the dumps or study material provided by them are authentic and up to date. They have a dedicated team to assist students and make sure they have a positive experience.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Dec 21, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Dec 22, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Question 27

You are the project manager for your company. You are working with the activities defined in the figure below.

Questions 27

What will happen to your project if Activity F takes five additional days to complete than what was expected?

Options:

A.

Your project's critical path will shift to ACFI.

B.

Your project will be late by five days.

C.

Your project can still complete on time as float is available on Activity I.

D.

Your project will now have two critical paths.