Question 16

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?

Options:

A.

To track the work to the project requirements

B.

To maintain profit and loss statements for the project

C.

To help the project team understand what work is required to be completed

D.

To communicate the work to be completed to the project stakeholders

Discussion
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Dec 6, 2025
Thanks for the recommendation! I'll check it out.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Dec 18, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie Dec 21, 2025
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Dec 4, 2025
They give you a competitive edge and help you prepare better.
Question 17

Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?

Options:

A.

Imminent activity management

B.

Predecessor-only diagramming

C.

Rolling wave planning

D.

Decomposition

Discussion
Question 18

You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?

Options:

A.

Crashing increases project costs.

B.

Crashing is a top-down approach to project completion.

C.

Crashing restricts resource utilization.

D.

Crashing always increases project risks.

Discussion
Question 19

Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

Options:

A.

Project final report

B.

Scope baseline

C.

Quality control mechanism

D.

Cost baseline

Discussion