Question 12

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

Options:

A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Discussion
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 14, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Sep 22, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Sep 3, 2025
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Sep 2, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Sep 20, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 13

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Discussion
Question 14

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

Options:

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Discussion
Question 15

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

Options:

A.

$950,000

B.

$2,375,000

C.

$1,055,543

D.

$938,260

Discussion