Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMI-SP Exam Questions and Answers by reagan

Page: 7 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: reagan
Question 28

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?

Options:

A.

-$29,350

B.

-$117,282

C.

-$938,260

D.

-$11,740

Discussion
Question 29

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

Options:

A.

Precedence Diagramming Method

B.

Schedule network template

C.

Dependency determination

D.

Activity on the Node

Discussion
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Sep 2, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Sep 7, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Robin
Cramkey is highly recommended.
Jonah Sep 1, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Sep 2, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Sep 25, 2025
Yeah, definitely. I experienced the same.
Question 30

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?

Options:

A.

Schedule compression

B.

Reserve analysis

C.

Variance analysis

D.

Expert judgment

Discussion
Question 31

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

Options:

A.

Lesson learned documentation

B.

Risk analysis

C.

Preventive action

D.

Corrective action

Discussion
Page: 7 / 11

PMI-SP
PDF

$42  $104.99

PMI-SP Testing Engine

$50  $124.99

PMI-SP PDF + Testing Engine

$66  $164.99