Big Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-SP Exam Questions and Answers by leonidas

Page: 2 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: leonidas
Question 8

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

Options:

A.

-$47,500

B.

0.89

C.

$427,500

D.

0.98

Discussion
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Nov 2, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Nov 15, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Nov 2, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Nov 10, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Question 9

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Options:

A.

Risk management plan

B.

Schedule management plan

C.

Risk register

D.

Activity attributes

Discussion
Question 10

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options:

A.

Decomposition

B.

Rolling wave plan

C.

Precedence diagramming method

D.

Templates

Discussion
Question 11

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Questions 11

Based on this diagram, find out the earliest day on which Activity G can be started.

Options:

A.

Day 13

B.

Day 7

C.

Day 22

D.

Day 17

Discussion
Page: 2 / 11

PMI-SP
PDF

$36.75  $104.99

PMI-SP Testing Engine

$43.75  $124.99

PMI-SP PDF + Testing Engine

$57.75  $164.99