Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-SP Exam Questions and Answers by leonidas

Page: 2 / 11

PMI PMI-SP Exam Overview :

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP Dumps
Vendor: PMI Certification: PMI Certification
Questions: 323 Q&A's Shared By: leonidas
Question 8

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

Options:

A.

-$47,500

B.

0.89

C.

$427,500

D.

0.98

Discussion
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Oct 25, 2024
That makes sense. What makes Cramkey Dumps different from other study materials?
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Aug 9, 2024
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 1, 2024
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Question 9

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

Options:

A.

Risk management plan

B.

Schedule management plan

C.

Risk register

D.

Activity attributes

Discussion
Question 10

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Options:

A.

Decomposition

B.

Rolling wave plan

C.

Precedence diagramming method

D.

Templates

Discussion
Question 11

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Questions 11

Based on this diagram, find out the earliest day on which Activity G can be started.

Options:

A.

Day 13

B.

Day 7

C.

Day 22

D.

Day 17

Discussion
Page: 2 / 11

PMI-SP
PDF

$36.75  $104.99

PMI-SP Testing Engine

$43.75  $124.99

PMI-SP PDF + Testing Engine

$57.75  $164.99