Big Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by benedict

Page: 18 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: benedict
Question 72

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

Options:

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Discussion
Question 73

In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product

What should the project manager do?

Options:

A.

Add this risk to the risk register and monitor it according to the risk management plan

B.

Escalate this to higher management and ask for help to resolve the issue.

C.

Impose the delivery dates on the software team leader and notify the functional manager about the situation

D.

Ask the software team leader to use a predictive approach and commit to a delivery date

Discussion
Question 74

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Discussion
Alessia
Amazing Dumps. Found almost all questions in actual exam whih I prepared from these valuable dumps. Recommended!!!!
Belle Sep 18, 2025
That's impressive. I've been struggling with finding good study material for my certification. Maybe I should give Cramkey Dumps a try.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 3, 2025
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Lennox
Something Special that they provide a comprehensive overview of the exam content. They cover all the important topics and concepts, so you can be confident that you are well-prepared for the test.
Aiza Sep 10, 2025
That makes sense. What makes Cramkey Dumps different from other study materials?
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 1, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Sep 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Question 75

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Discussion
Page: 18 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599