Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by izabela

Page: 45 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: izabela
Question 180

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

Options:

A.

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

B.

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.

C.

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.

D.

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.

Discussion
Question 181

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?

Options:

A.

This framework is not appropriate for agile.

B.

This is a learning experience for the agile team.

C.

An agile approach is easily adaptable.

D.

An agile approach is different.

Discussion
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Dec 28, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Nia
Why are these Dumps so important for students these days?
Mary Dec 19, 2025
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Dec 24, 2025
YES….. I saw the same questions in the exam.
Hassan
Highly Recommended Dumps… today I passed my exam! Same questions appear. I bought Full Access.
Kasper Dec 22, 2025
Hey wonderful….so same questions , sounds good. Planning to write this week, I will go for full access today.
Question 182

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?

Options:

A.

Ask the team if they can do the work until there is an available supplier.

B.

Train the supplier in agile approaches to help them understand the contract.

C.

Issue a request for proposal (RFP) to find new suppliers with agile experience.

D.

Change contract terms and conditions to avoid losing the supplier.

Discussion
Question 183

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Discussion
Page: 45 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599