Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by gabrielle

Page: 16 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: gabrielle
Question 64

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems ontheir own.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity

D.

Recommend to the project team members that they should improve their planningand make their stones smaller

Discussion
Question 65

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

Options:

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Discussion
Question 66

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Discussion
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Dec 28, 2025
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Dec 18, 2025
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Cody
I used Cramkey Dumps to prepare and a lot of the questions on the exam were exactly what I found in their study materials.
Eric Dec 2, 2025
Really? That's great to hear! I used Cramkey Dumps too and I had the same experience. The questions were almost identical.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Dec 6, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Dec 3, 2025
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Question 67

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Discussion
Page: 16 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599