New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by angus

Page: 21 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: angus
Question 84

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?

Options:

A.

Schedule meetings with the customer to determine their ability to support multiple incremental deliveries

B.

Work with the agile team to schedule the incremental deliveries to enable deliveryof business value sooner to the customer.

C.

Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries

D.

Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Nov 10, 2025
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Nov 2, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Nov 12, 2025
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Nov 26, 2025
Thanks for the recommendation! I'll check it out.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Nov 26, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Question 85

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

Options:

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Discussion
Question 86

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Discussion
Question 87

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

Options:

A.

Share this opportunity with another project

B.

Establish a contingency reserve to support the opportunity

C.

Further monitor the opportunity

D.

No more action is required

Discussion
Page: 21 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599