Question 196

In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.

Which conflict resolution approach did the project manager use?

Options:

A.

Compromise

B.

Collaborate

C.

Synergy

D.

Force

Discussion
Nell
Are these dumps reliable?
Ernie Jan 20, 2026
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Jan 7, 2026
They give you a competitive edge and help you prepare better.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Jan 22, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Jan 23, 2026
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Question 197

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

Options:

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Discussion
Question 198

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Discussion
Question 199

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?

Options:

A.

Invite the new manager to the next daily scrum.

B.

Invite the new manager to the next sprint review.

C.

Invite the new manager to the next sprint planning.

D.

Invite the new manager to the next sprint retrospective.