Big Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by winston

Page: 49 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: winston
Question 196

In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.

Which conflict resolution approach did the project manager use?

Options:

A.

Compromise

B.

Collaborate

C.

Synergy

D.

Force

Discussion
Question 197

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

Options:

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Discussion
Question 198

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

Options:

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Oct 5, 2025
That's great to hear. I am going to try them soon.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Oct 2, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Oct 16, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Sarah
Yeah, I was so relieved when I saw that the question appeared in the exam were similar to their exam dumps. It made the exam a lot easier and I felt confident going into it.
Aaliyah Oct 22, 2025
Same here. I've heard mixed reviews about using exam dumps, but for us, it definitely paid off.
Question 199

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?

Options:

A.

Invite the new manager to the next daily scrum.

B.

Invite the new manager to the next sprint review.

C.

Invite the new manager to the next sprint planning.

D.

Invite the new manager to the next sprint retrospective.

Discussion
Page: 49 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599