| Exam Name: | Project Management Professional (2025 Version) | ||
| Exam Code: | PMP Dumps | ||
| Vendor: | PMI | Certification: | Project-Management-Professional |
| Questions: | 2040 Q&A's | Shared By: | winston |
In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.
Which conflict resolution approach did the project manager use?
A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.
What should the project manager do?
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
What should the project manager do first to get the team energized and performing efficiently?
A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.
What should the project manager do?