Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by niko

Page: 48 / 127

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2024 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1702 Q&A's Shared By: niko
Question 192

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

Options:

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Discussion
Question 193

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Questions 193

Options:

Discussion
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Oct 24, 2024
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Aug 25, 2024
That's great. I think I'll give Cramkey Dumps a try.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 26, 2024
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 194

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Discussion
Question 195

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Discussion
Page: 48 / 127
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599