Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMP Exam Questions and Answers by haider

Page: 39 / 140

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1877 Q&A's Shared By: haider
Question 156

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Discussion
Question 157

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Discussion
Lennie
I passed my exam and achieved wonderful score, I highly recommend it.
Emelia Oct 2, 2024
I think I'll give Cramkey a try next time I take a certification exam. Thanks for the recommendation!
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Oct 25, 2024
Good point. Thanks for the advice. I'll definitely keep that in mind.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 29, 2024
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Question 158

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Discussion
Question 159

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Discussion
Page: 39 / 140
Title
Questions
Posted

PMP
PDF

$159.6  $399

PMP Testing Engine

$179.6  $449

PMP PDF + Testing Engine

$239.6  $599