Question 148

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Discussion
Question 149

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

Options:

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Discussion
Question 150

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Discussion
Question 151

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Discussion
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Dec 10, 2025
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Dec 13, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Dec 26, 2025
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Dec 20, 2025
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Dec 6, 2025
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Page: 37 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599