Question 148

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 17, 2025
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 14, 2025
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Conor
I recently used these dumps for my exam and I must say, I was impressed with their authentic material.
Yunus Sep 11, 2025
Exactly…….The information in the dumps is so authentic and up-to-date. Plus, the questions are very similar to what you'll see on the actual exam. I felt confident going into the exam because I had studied using Cramkey Dumps.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Aug 31, 2025
did you use PDF or Engine? Which one is most useful?
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Sep 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Question 149

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

Options:

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Discussion
Question 150

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Discussion
Question 151

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Discussion