Question 124

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Discussion
Ari
Can anyone explain what are these exam dumps and how are they?
Ocean Jan 4, 2026
They're exam preparation materials that are designed to help you prepare for various certification exams. They provide you with up-to-date and accurate information to help you pass your exams.
Anya
I must say they're considered the best dumps available and the questions are very similar to what you'll see in the actual exam. Recommended!!!
Cassius Jan 3, 2026
Yes, they offer a 100% success guarantee. And many students who have used them have reported passing their exams with flying colors.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Jan 27, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Laila
They're such a great resource for anyone who wants to improve their exam results. I used these dumps and passed my exam!! Happy customer, always prefer. Yes, same questions as above I know you guys are perfect.
Keira Jan 7, 2026
100% right….And they're so affordable too. It's amazing how much value you get for the price.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Jan 4, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 125

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

Options:

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Discussion
Question 126

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

Options:

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Discussion
Question 127

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

Discussion