Question 124

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Discussion
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Nov 18, 2025
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Nov 25, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Nov 7, 2025
That's great. I think I'll give Cramkey Dumps a try.
Nell
Are these dumps reliable?
Ernie Nov 23, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Question 125

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

Options:

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Discussion
Question 126

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

Options:

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Discussion
Question 127

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

Discussion