Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by gabriela

Page: 34 / 159

PMI PMP Exam Overview :

Exam Name: Project Management Professional (PMBOK 7th Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2134 Q&A's Shared By: gabriela
Question 136

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.

What should the project manager do first?

Options:

A.

Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).

B.

Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.

C.

Ask the scrum master to identify why sprints are in process for work that is not on the critical path.

D.

Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.

Discussion
Question 137

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

Options:

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

Discussion
Question 138

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?

Options:

A.

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.

B.

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.

C.

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.

D.

Explain that each individual newsletter is based on specific categories of communication for the intended audience.

Discussion
Question 139

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.

Align the project goals with the team member.

B.

Reassign the team member to another project.

C.

Nominate the team member to receive agile training.

D.

Allocate another resource to support the team member.

Discussion
Atlas
What are these Dumps? Would anybody please explain it to me.
Reign Feb 4, 2026
These are exam dumps for a variety of IT certifications. They have a vast collection of updated questions and answers, which are very helpful in preparing for the exams.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Feb 25, 2026
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Feb 16, 2026
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Feb 8, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Page: 34 / 159
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599