New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by maverick

Page: 33 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: maverick
Question 132

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

Options:

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer's priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

Discussion
Question 133

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback'?

Options:

A.

Assessed and analyzed personality indicators from the project team

B.

Sent the activity details to everyone involved prior to the session

C.

Communicated the decision to conduct this activity to the key team stakeholders

D.

Selected a vendor for the activity according to the procurement management plan

Discussion
Question 134

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.

Update the risk register and implement the approved risk response plan for qualitydeviations.

B.

Identify the resources that were responsible for the deliverable and request a teamdevelopment plan.

C.

Update the issue log, identify the involved stakeholders, and assign resources to thecorrective actions.

D.

Submit a change request to update the project quality requirements for the involvedproject deliverable.

Discussion
Robin
Cramkey is highly recommended.
Jonah Nov 26, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Nov 25, 2025
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Nov 19, 2025
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Nov 10, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Question 135

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

Options:

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Discussion
Page: 33 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599