Question 76

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

Options:

A.

Work with the procurement team to find alternative options.

B.

Contact the vendor that supplied similar equipment for a previous project.

C.

Use the existing equipment and replace it later with the new equipment

D.

Ask the project sponsor to expedite the vendor selection process.

Discussion
Question 77

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

Options:

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.

B.

Establish a pull communications method to access knowledge repositories and lessons learned.

C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.

D.

Establish a push communications method for the team to share knowledge and lessons learned.

Discussion
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie (not set)
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun (not set)
That sounds really useful. I'll definitely check it out.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony (not set)
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Inaaya
Are these Dumps worth buying?
Fraser (not set)
Yes, of course, they are necessary to pass the exam. They give you an insight into the types of questions that could come up and help you prepare effectively.
Question 78

Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.

How should the project manager impartially prioritize the requirements to be integrated?

Options:

A.

Retain only requirements that result in profitable revenue growth.

B.

Ensure the CEO selects the requirements from all department leaders.

C.

Give each department a fixed budget that will cover ten requirements.

D.

Rank the requirements with the highest benefit-cost ratio as more important.

Discussion
Question 79

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

Options:

A.

Refer to the requirements traceability matrix and analyze the requirement.

B.

Analyze the benefits management plan and implement the needed change.

C.

Consult the scope management plan with the customer to understand the gap.

D.

Discuss and agree with the customer to implement the missing requirement.