Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: big60

PMI Updated PMP Exam Questions and Answers by nansi

Page: 20 / 140

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 1877 Q&A's Shared By: nansi
Question 80

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Discussion
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Oct 14, 2024
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Zayaan
Successfully aced the exam… Thanks a lot for providing amazing Exam Dumps.
Harmony Sep 10, 2024
That's fantastic! I'm glad to hear that their dumps helped you. I also used them and found it accurate.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Oct 2, 2024
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Aug 29, 2024
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Question 81

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Discussion
Question 82

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Discussion
Question 83

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

Options:

A.

Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

B.

Ask the sponsor for support regarding the allocation of additional resources to finish on time.

C.

Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources.

D.

Meet with the customer to agree on the components of the solution and the priorities.

Discussion
Page: 20 / 140
Title
Questions
Posted

PMP
PDF

$159.6  $399

PMP Testing Engine

$179.6  $449

PMP PDF + Testing Engine

$239.6  $599