Big Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMP Exam Questions and Answers by nansi

Page: 20 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: nansi
Question 80

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Options:

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

Discussion
Andrew
Are these dumps helpful?
Jeremiah Sep 25, 2025
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Sep 11, 2025
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Rosalie
I passed. I would like to tell all students that they should definitely give Cramkey Dumps a try.
Maja Sep 22, 2025
That sounds great. I'll definitely check them out. Thanks for the suggestion!
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 26, 2025
That sounds really useful. I'll definitely check it out.
Question 81

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Discussion
Question 82

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

Options:

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.

Inform the stakeholders that the project will be delayed due to previous team management

C.

Crash the project timeline to ensure the project is back on schedule

D.

Issue a change request to extend the project schedule based on identified delays

Discussion
Question 83

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.

Develop a business case with assumptions for the new model

B.

Develop a communications management plan to inform the employees about the new business model

C.

Adopt an iterative rollout approach that delivers the highest business value earlier

D.

Develop a detailed sprint plan with clear deliverables

Discussion
Page: 20 / 152
Title
Questions
Posted

PMP
PDF

$139.65  $399

PMP Testing Engine

$157.15  $449

PMP PDF + Testing Engine

$209.65  $599