Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: cram70off

PMI Updated PMP Exam Questions and Answers by saskia

Page: 44 / 152

PMI PMP Exam Overview :

Exam Name: Project Management Professional (2025 Version)
Exam Code: PMP Dumps
Vendor: PMI Certification: Project-Management-Professional
Questions: 2040 Q&A's Shared By: saskia
Question 176

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

Options:

A.

Allow project B's leader to continue building relationships.

B.

Talk with project B's leader to discuss possible impacts to both projects.

C.

Tell project A's team member to ignore project B's leader.

D.

Ensure project A's team member can finish the work committed to project A.

Discussion
Question 177

During a project's execution phase, the team faced a setback in one of the deliveries and was asked to come up with a new plan. All team members joined a meeting to address the issue and, after a while, the project manager observed that two members of the team were just agreeing with anything that was proposed even though they were opposed to the outcome.

What conflict resolution style were the team members adopting?

Options:

A.

Avoidant style

B.

Combative style

C.

Collaborative style

D.

Accommodative style

Discussion
Question 178

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

Options:

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

Discussion
Question 179

An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

Options:

A.

Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.

B.

Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.

C.

Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.

D.

Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Dec 2, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Dec 25, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Robin
Cramkey is highly recommended.
Jonah Dec 2, 2025
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Dec 15, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Page: 44 / 152
Title
Questions
Posted

PMP
PDF

$119.7  $399

PMP Testing Engine

$134.7  $449

PMP PDF + Testing Engine

$179.7  $599