Question 88

A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.

What should the project manager do next?

Options:

A.

Engage with the functional manager to discuss details to obtain the required support.

B.

Request a teleconference meeting with the sponsor to submit a change request to allow the development team to conduct testing.

C.

Discuss testing requirements at the weekly project meeting to negotiate the best approach to test software.

D.

Send an email to the procurement specialist to negotiate with a company that specializes in software testing.

Discussion
Question 89

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Discussion
Question 90

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Discussion
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 21, 2024
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 29, 2024
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Sep 15, 2024
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.
Robin
Cramkey is highly recommended.
Jonah Oct 16, 2024
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 91

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Discussion