IIBA Updated CCBA Exam Questions and Answers by reece

Page: 33 / 47

IIBA CCBA Exam Overview :

Exam Name: Certification of Capability in Business Analysis (CCBA)
Exam Code: CCBA Dumps
Vendor: IIBA Certification: Certification of Capability in Business Analysis
Questions: 638 Q&A's Shared By: reece
Question 132

Project work is taking place to evaluate whether a system's requirements can be met via creating internally, purchasing from others, or a combination of the two. What goal is addressed by this analysis?

Options:

A.

Developing the project plan

B.

Outlining the change control strategy

C.

Defining the solution approach

D.

Validating the requirements

Discussion
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus Aug 5, 2026
YES….. I saw the same questions in the exam.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Aug 16, 2026
That's great to hear. I am going to try them soon.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Aug 6, 2026
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Amy
I passed my exam and found your dumps 100% relevant to the actual exam.
Lacey Aug 15, 2026
Yeah, definitely. I experienced the same.
Question 133

The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (6A) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?

Options:

A.

Traceability matrices

B.

IEEE /ISO 29148 requirements standards

C.

Additional requirements attributes

D.

Matrix documentation formats

Discussion
Question 134

A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?

Options:

A.

Ensure test scenarios conform to business requirements

B.

Choose an appropriate format to communicate requirements

C.

Analyze requirements to remove unnecessary components

D.

Align business requirements to organizational strategy

Discussion
Question 135

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?

Options:

A.

Concept modelling

B.

Requirements architecture

C.

Backlog management

D.

Balanced scorecard

Discussion