Question 40

A business analyst (BA) works for a financial institution that wants to acquire new systems and migrate all future business operations to the new systems. The BA is responsible for performing a gap analysis and has reviewed the current state of systems.

What is the next task that the BA needs to do to complete the gap analysis?

Options:

A.

Identify performance measures

B.

Define the future state capabilities

C.

Categorize risks factors

D.

Select the stakeholder engagement approach

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Sep 6, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Robin
Cramkey is highly recommended.
Jonah Sep 26, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Sep 10, 2026
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Aryan
Absolutely rocked! They are an excellent investment for anyone who wants to pass the exam on the first try. They save you time and effort by providing a comprehensive overview of the exam content, and they give you a competitive edge by giving you access to the latest information. So, I definitely recommend them to new students.
Jessie Sep 9, 2026
did you use PDF or Engine? Which one is most useful?
Question 41

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Options:

A.

RACI chart

B.

Pareto chart

C.

Resource histogram chart

D.

Organization chart

Discussion
Question 42

Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

Options:

A.

Work breakdown structure (WBS)

B.

WBS dictionary

C.

Project scope statement

D.

Project charter

Discussion
Question 43

The objective of a solution implemented was to increase the number of customer calls resolved per hour.

When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?

Options:

A.

Metrics and Key Performance Indicators (KPIs)

B.

Frequency and Timing

C.

Financial Analysis

D.

Benchmarking and Market Analysis

Discussion