Question 40

A business analyst (BA) works for a financial institution that wants to acquire new systems and migrate all future business operations to the new systems. The BA is responsible for performing a gap analysis and has reviewed the current state of systems.

What is the next task that the BA needs to do to complete the gap analysis?

Options:

A.

Identify performance measures

B.

Define the future state capabilities

C.

Categorize risks factors

D.

Select the stakeholder engagement approach

Discussion
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Jul 4, 2026
That’s great!!! I’ll definitely give it a try. Thanks!!!
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Jul 10, 2026
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Jul 4, 2026
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Jul 11, 2026
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Syeda
I passed, Thank you Cramkey for your precious Dumps.
Stella Jul 14, 2026
That's great. I think I'll give Cramkey Dumps a try.
Question 41

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Options:

A.

RACI chart

B.

Pareto chart

C.

Resource histogram chart

D.

Organization chart

Discussion
Question 42

Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

Options:

A.

Work breakdown structure (WBS)

B.

WBS dictionary

C.

Project scope statement

D.

Project charter

Discussion
Question 43

The objective of a solution implemented was to increase the number of customer calls resolved per hour.

When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?

Options:

A.

Metrics and Key Performance Indicators (KPIs)

B.

Frequency and Timing

C.

Financial Analysis

D.

Benchmarking and Market Analysis

Discussion