Question 40

A business analyst (BA) works for a financial institution that wants to acquire new systems and migrate all future business operations to the new systems. The BA is responsible for performing a gap analysis and has reviewed the current state of systems.

What is the next task that the BA needs to do to complete the gap analysis?

Options:

A.

Identify performance measures

B.

Define the future state capabilities

C.

Categorize risks factors

D.

Select the stakeholder engagement approach

Discussion
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Apr 16, 2026
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Apr 18, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Apr 4, 2026
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Robin
Cramkey is highly recommended.
Jonah Apr 11, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Question 41

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Options:

A.

RACI chart

B.

Pareto chart

C.

Resource histogram chart

D.

Organization chart

Discussion
Question 42

Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

Options:

A.

Work breakdown structure (WBS)

B.

WBS dictionary

C.

Project scope statement

D.

Project charter

Discussion
Question 43

The objective of a solution implemented was to increase the number of customer calls resolved per hour.

When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?

Options:

A.

Metrics and Key Performance Indicators (KPIs)

B.

Frequency and Timing

C.

Financial Analysis

D.

Benchmarking and Market Analysis

Discussion