Question 40

A business analyst (BA) works for a financial institution that wants to acquire new systems and migrate all future business operations to the new systems. The BA is responsible for performing a gap analysis and has reviewed the current state of systems.

What is the next task that the BA needs to do to complete the gap analysis?

Options:

A.

Identify performance measures

B.

Define the future state capabilities

C.

Categorize risks factors

D.

Select the stakeholder engagement approach

Discussion
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Jan 4, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Jan 9, 2026
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Jan 22, 2026
Good point. Thanks for the advice. I'll definitely keep that in mind.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Jan 8, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Question 41

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Options:

A.

RACI chart

B.

Pareto chart

C.

Resource histogram chart

D.

Organization chart

Discussion
Question 42

Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

Options:

A.

Work breakdown structure (WBS)

B.

WBS dictionary

C.

Project scope statement

D.

Project charter

Discussion
Question 43

The objective of a solution implemented was to increase the number of customer calls resolved per hour.

When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?

Options:

A.

Metrics and Key Performance Indicators (KPIs)

B.

Frequency and Timing

C.

Financial Analysis

D.

Benchmarking and Market Analysis