IIBA Updated CBAP Exam Questions and Answers by sana

Page: 10 / 37

IIBA CBAP Exam Overview :

Exam Name: Certified Business Analysis Professional
Exam Code: CBAP Dumps
Vendor: IIBA Certification: Certified Business Analysis Professional
Questions: 497 Q&A's Shared By: sana
Question 40

A business analyst (BA) works for a financial institution that wants to acquire new systems and migrate all future business operations to the new systems. The BA is responsible for performing a gap analysis and has reviewed the current state of systems.

What is the next task that the BA needs to do to complete the gap analysis?

Options:

A.

Identify performance measures

B.

Define the future state capabilities

C.

Categorize risks factors

D.

Select the stakeholder engagement approach

Discussion
Yusra
I passed my exam. Cramkey Dumps provides detailed explanations for each question and answer, so you can understand the concepts better.
Alisha Jul 9, 2025
I recently used their dumps for the certification exam I took and I have to say, I was really impressed.
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Jul 16, 2025
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Jul 17, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Jul 2, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Question 41

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Options:

A.

RACI chart

B.

Pareto chart

C.

Resource histogram chart

D.

Organization chart

Discussion
Question 42

Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?

Options:

A.

Work breakdown structure (WBS)

B.

WBS dictionary

C.

Project scope statement

D.

Project charter

Discussion
Question 43

The objective of a solution implemented was to increase the number of customer calls resolved per hour.

When using basic statistical sampling concepts, what does the business analyst (BA) need to consider?

Options:

A.

Metrics and Key Performance Indicators (KPIs)

B.

Frequency and Timing

C.

Financial Analysis

D.

Benchmarking and Market Analysis

Discussion