Question 88

A company is reconfiguring its business processes to improve the quality of its products and lower operational costs. This includes defining metrics that will be used to evaluate the effectiveness of future change strategy. Which of the following techniques achieves this goal?

Options:

A.

Decision modeling

B.

financial analysis

C.

Business case

D.

Balanced storecard

Discussion
Question 89

After having created several prototypes of a new. web-based application, a business analyst (BA) would like to meet with the organization's stakeholders to elicit their perception ideas, and attitudes about the prototypes Which of the following techniques should the SA use?

Options:

A.

Decision Analysis

B.

Prioritization

C.

Brainstorming

D.

focus Groups

Discussion
Question 90

A conservative company with rigorous risk control plans and internal audit rules has a recurrent problem with a core Business application. As a result access to this application must be restricted and controlled and maintenance must be on-site. However, the company feels that the application must have an emergency service team. The routine maintenance of this solution is provided by an external vendor and the vendor requested 24 hours remote access to quality and production data. In this context what is the company's response to the vendor's request?

Options:

A.

Dented because of the company’s risk aversion

B.

Accepted, because the company has an urgent problem to solve

C.

Denied- because the vendor requested it

D.

Accepted, because immediate remote access will resolve any issue

Discussion
Question 91

You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor.

Which of these stakeholders will be responsible for writing the project scope?

Options:

A.

Domain subject matter expert

B.

Business analyst

C.

Project manager

D.

Sponsor

Discussion
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Oct 2, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Oct 8, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Oct 9, 2025
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Oct 2, 2025
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Oct 16, 2025
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Page: 22 / 37
Title
Questions
Posted

CBAP
PDF

$36.75  $104.99

CBAP Testing Engine

$43.75  $124.99

CBAP PDF + Testing Engine

$57.75  $164.99