Question 156

An enterprise's board of directors can BEST manage enterprise risk by:

Options:

A.

mandating board-approved enterprise risk management (ERM) modifications.

B.

requiring the establishment of an enterprise risk management (ERM) framework.

C.

requiring the establishment of an enterprise-wide program management office.

D.

ensuring the cost-effectiveness of the internal control system.

Discussion
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Oct 11, 2025
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Oct 16, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Oct 2, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Oct 15, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Question 157

A rail transport company has the worst on-time arrival record in the industry due to an antiquated IT system that controls scheduling. Despite employee resistance, an initiative lo upgrade the technology and related processes has been approved. To maximize employee engagement throughout the project, which of the following should be in place prior to the start of the initiative?

Options:

A.

Procurement management plan

B.

Organizational change management plan

C.

Risk response plan

D.

Resource management plan

Discussion
Question 158

Which of the following BEST reflects mature risk management in an enterprise?

Options:

A.

A regularly updated risk register

B.

Ongoing risk assessment

C.

Ongoing investment in risk mitigation

D.

Responsive risk awareness culture

Discussion
Question 159

The board of directors has mandated the use of geolocation software to track mobile assets assigned to employees who travel outside of their home country. To comply with this mandate, the IT steering committee should FIRST request

Options:

A.

the inclusion of mandatory training for remote device users.

B.

an architectural review to determine appropriate solution design.

C.

an assessment to determine if data privacy protection is addressed.

D.

an update to the acceptable use policy.

Discussion