New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-ACP Exam Questions and Answers by josh

Page: 2 / 35

PMI PMI-ACP Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-ACP Dumps
Vendor: PMI Certification: PMI Agile
Questions: 482 Q&A's Shared By: josh
Question 8

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

Options:

A.

Reduced or improper customer collaboration.

B.

Reduced or improper product knowledge by the development team.

C.

Reduced or improper release planning.

D.

Reduced or improper product specification.

Discussion
Question 9

Several team members have complained to senior management about their scrum master's processes. What should the scrum master do to address the team's process concerns?

Options:

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Dec 17, 2025
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Dec 3, 2025
That's great to hear. I am going to try them soon.
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Dec 21, 2025
That sounds really useful. I'll definitely check it out.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy Dec 22, 2025
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Dec 13, 2025
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Question 10

The agile team has failed to meet their iteration goal, and contention has developed between members. The agile leader would like to determine how to improve the team's productivity and morale.

How should the agile leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Discussion
Question 11

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Discussion
Page: 2 / 35
Title
Questions
Posted

PMI-ACP
PDF

$36.75  $104.99

PMI-ACP Testing Engine

$43.75  $124.99

PMI-ACP PDF + Testing Engine

$57.75  $164.99