Question 8

What should the Scrum Master do?

Options:

A.

Meet with the team to gain alignment with the legal department ' s need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project ' s trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Discussion
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Sep 6, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Sep 25, 2026
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Melody
My experience with Cramkey was great! I was surprised to see that many of the questions in my exam appeared in the Cramkey dumps.
Colby Sep 11, 2026
Yes, In fact, I got a score of above 85%. And I attribute a lot of my success to Cramkey's dumps.
Freddy
I passed my exam with flying colors and I'm confident who will try it surely ace the exam.
Aleksander Sep 1, 2026
Thanks for the recommendation! I'll check it out.
Question 9

The project manager has requested that the customer participate in the requirements gathering session for the next release. A conflict comes up regarding the requirements between the customer and team.

What should the project manager do?

Options:

A.

Based on value to the organization, the project manager should decide what can be included or not in the final requirements.

B.

The customer is the end user of the product and should have the authority to decide about the product requirements.

C.

The project manager should discuss the requirements with the customer alone so that the team can deliver the prioritized requirements.

D.

Encourage self-organization by communicating the importance of a collaborative approach in decision making about the requirements.

Discussion
Question 10

How should the agile practitioner address this?

Options:

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Discussion
Question 11

What do the principles of Extreme Programming (XP) include?

Options:

A.

Communication, respect, and courage

B.

Communication, process flow, and authoritarian structure

C.

Value people over processes, communication, respect disagreement, and strive for consensus

D.

Rapid feedback, assume simplicity, incremental change, embrace change, and quality work