Question 8

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

Options:

A.

Reduced or improper customer collaboration.

B.

Reduced or improper product knowledge by the development team.

C.

Reduced or improper release planning.

D.

Reduced or improper product specification.

Discussion
Question 9

Several team members have complained to senior management about their scrum master's processes. What should the scrum master do to address the team's process concerns?

Options:

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

Discussion
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Jan 8, 2026
That's great to hear. I am going to try them soon.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Jan 21, 2026
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Neve
Will I be able to achieve success after using these dumps?
Rohan Jan 27, 2026
Absolutely. It's a great way to increase your chances of success.
Ayra
How these dumps are necessary for passing the certification exam?
Damian Jan 7, 2026
They give you a competitive edge and help you prepare better.
Question 10

The agile team has failed to meet their iteration goal, and contention has developed between members. The agile leader would like to determine how to improve the team's productivity and morale.

How should the agile leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Discussion
Question 11

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.