Question 48

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team ' s estimated velocity.

Discussion
Question 49

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.

What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Discussion
Question 50

What should the Scrum Master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story ' s technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story ' s priority and wait until more technical details are available.

Discussion
Andrew
Are these dumps helpful?
Jeremiah Sep 19, 2026
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Sep 14, 2026
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Sep 19, 2026
That sounds really useful. I'll definitely check it out.
Pippa
I was so happy to see that almost all the questions on the exam were exactly what I found in their Dumps.
Anastasia Sep 23, 2026
You are right…It was amazing! The Cramkey Dumps were so comprehensive and well-organized, it made studying for the exam a breeze.
Ivan
I tried these dumps for my recent certification exam and I found it pretty helpful.
Elis Aug 31, 2026
Agree!!! The questions in the dumps were quite similar to what came up in the actual exam. It gave me a good idea of the types of questions to expect and helped me revise efficiently.
Question 51

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master ' s estimation

B.

Identify a set of user stories based on the team ' s velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion