Question 116

An agile learn has been in place (or five years and the customer is satisfied with the team's performance and deliverables. Now that the product is buill and delivered, the customer is considering the future role of the Scrum Master.

What should the customer do?

Options:

A.

Expand the Scrum Master's role to other projects, while allowing them to support the current project.

B.

Release the Scrum Master, since the team is adequately skilled with agile practices.

C.

Expand the product owner's role to serve as the Scrum Master, while providing additional product knowledge.

D.

Increase the functional manager's role to act as the Scrum Master, while providing additional information about functional areas.

Discussion
Question 117

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

Options:

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Discussion
Question 118

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

Options:

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Discussion
Andrew
Are these dumps helpful?
Jeremiah Oct 27, 2024
Yes, Don’t worry!!! I'm confident you'll find them to be just as helpful as I did. Good luck with your exam!
Ayesha
They are study materials that are designed to help students prepare for exams and certification tests. They are basically a collection of questions and answers that are likely to appear on the test.
Ayden Oct 16, 2024
That sounds interesting. Why are they useful? Planning this week, hopefully help me. Can you give me PDF if you have ?
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Sep 19, 2024
Great. Yes they are really effective
Nia
Why are these Dumps so important for students these days?
Mary Oct 9, 2024
With the constantly changing technology and advancements in the industry, it's important for students to have access to accurate and valid study material. Cramkey Dumps provide just that. They are constantly updated to reflect the latest changes and ensure that the information is up-to-date.
Question 119

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.

Speak to the agile lead about the concerns.

B.

Follow the agile lead's instructions.

C.

Increase the time worked to meet objectives.

D.

Speak to all team members about the concerns.

Discussion
Page: 29 / 35
Title
Questions
Posted

PMI-ACP
PDF

$36.75  $104.99

PMI-ACP Testing Engine

$43.75  $124.99

PMI-ACP PDF + Testing Engine

$57.75  $164.99