Question 116

An agile learn has been in place (or five years and the customer is satisfied with the team's performance and deliverables. Now that the product is buill and delivered, the customer is considering the future role of the Scrum Master.

What should the customer do?

Options:

A.

Expand the Scrum Master's role to other projects, while allowing them to support the current project.

B.

Release the Scrum Master, since the team is adequately skilled with agile practices.

C.

Expand the product owner's role to serve as the Scrum Master, while providing additional product knowledge.

D.

Increase the functional manager's role to act as the Scrum Master, while providing additional information about functional areas.

Discussion
Question 117

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

Options:

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Discussion
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Jul 20, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Jul 7, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Jul 12, 2025
That sounds really useful. I'll definitely check it out.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Jul 20, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 118

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

Options:

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Discussion
Question 119

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.

Speak to the agile lead about the concerns.

B.

Follow the agile lead's instructions.

C.

Increase the time worked to meet objectives.

D.

Speak to all team members about the concerns.