Question 76

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.

Influence the customer

B.

Mention the idea at the next retrospective

C.

Show the customer how much time and money would be saved

D.

Present the idea at the next ceremony attended by stakeholders to obtain their input

Discussion
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jan 23, 2026
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Josie
I just passed my certification exam using their dumps and I must say, I was thoroughly impressed.
Fatimah Jan 4, 2026
You’re right. The dumps were authentic and covered all the important topics. I felt confident going into the exam and it paid off.
Nadia
Why these dumps are important? Can I pass my exam without these dumps?
Julian Jan 19, 2026
The questions in the Cramkey dumps are explained in detail and there are also study notes and reference materials provided. This made it easier for me to understand the concepts and retain the information better.
Hendrix
Great website with Great Exam Dumps. Just passed my exam today.
Luka Jan 14, 2026
Absolutely. Cramkey Dumps only provides the latest and most updated exam questions and answers.
Question 77

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

Options:

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Discussion
Question 78

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value C. Recommend cancelling the current iteration and plan the change request into the next iteration.

C.

Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Discussion
Question 79

A project team identifies a number of technical challenges with features in the next sprint What should they do?

Options:

A.

Request direction from the technical manager

B.

Encourage the product owner to reallocate the features to another sprint

C.

determine who is best qualified to address the challenges

D.

Ask the product owner to assign the tasks to the most appropriately skilled resources

Discussion