Question 88

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

Options:

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.

Discussion
Question 89

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Discussion
Question 90

When a team member encounters an issue in an agile environment, what should they do?

Options:

A.

Limit communication between the team members and the customer to prevent unnecessary anxiety

B.

Manage communication between all team members and the customer to promote effective and transparent collaboration

C.

Manage communication between a few team members and the customer so that they may convey information to other team members

D.

Facilitate one-on-one communication between team members to reduce conflict and inefficiencies

Discussion
Honey
I highly recommend it. They made a big difference for me and I'm sure they'll help you too. Just make sure to use them wisely and not solely rely on them. They should be used as a supplement to your regular studies.
Antoni Sep 16, 2025
Good point. Thanks for the advice. I'll definitely keep that in mind.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Sep 9, 2025
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Sep 22, 2025
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Reeva
Wow what a success I achieved today. Thank you so much Cramkey for amazing Dumps. All students must try it.
Amari Sep 14, 2025
Wow, that's impressive. I'll definitely keep Cramkey in mind for my next exam.
Stefan
Thank you so much Cramkey I passed my exam today due to your highly up to date dumps.
Ocean Sep 7, 2025
Agree….Cramkey Dumps are constantly updated based on changes in the exams. They also have a team of experts who regularly review the materials to ensure their accuracy and relevance. This way, you can be sure you're studying the most up-to-date information available.
Question 91

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.