Question 88

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

Options:

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.

Discussion
Ava-Rose
Yes! Cramkey Dumps are amazing I passed my exam…Same these questions were in exam asked.
Ismail Sep 18, 2024
Wow, that sounds really helpful. Thanks, I would definitely consider these dumps for my certification exam.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Ella-Rose
Amazing website with excellent Dumps. I passed my exam and secured excellent marks!!!
Alisha Aug 17, 2024
Extremely accurate. They constantly update their materials with the latest exam questions and answers, so you can be confident that what you're studying is up-to-date.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Aug 18, 2024
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Question 89

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Discussion
Question 90

When a team member encounters an issue in an agile environment, what should they do?

Options:

A.

Limit communication between the team members and the customer to prevent unnecessary anxiety

B.

Manage communication between all team members and the customer to promote effective and transparent collaboration

C.

Manage communication between a few team members and the customer so that they may convey information to other team members

D.

Facilitate one-on-one communication between team members to reduce conflict and inefficiencies

Discussion
Question 91

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.