Question 120

An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" - a story-telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.

What is the project leader trying to create?

Options:

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other's weaknesses and strengths.

Discussion
Question 121

A team using Kanban identifies that their cycle time has significant variation After brainstorming the team determines that the root cause is the stones' varying sizes and risks.

What should the team do?

Options:

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stones

C.

Set a policy to break down stories larger than a specified complexity then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

Discussion
Question 122

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

Options:

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Discussion
Question 123

An agile team is planning the next iteration for a product release that has accumulated technical debt What should the team do?

Options:

A.

Add code cleanup activities to the product backlog and request prioritization by the product owner

B.

Add code cleanup activities to the next iteration and request clarification from the product owner

C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration

D.

Add code cleanup activities to the next release backlog and request documentation from the product owner

Discussion
Neve
Will I be able to achieve success after using these dumps?
Rohan Jul 14, 2025
Absolutely. It's a great way to increase your chances of success.
Kylo
What makes Cramkey Dumps so reliable? Please guide.
Sami Jul 24, 2025
Well, for starters, they have a team of experts who are constantly updating their material to reflect the latest changes in the industry. Plus, they have a huge database of questions and answers, which makes it easy to study and prepare for the exam.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Jul 20, 2025
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Ernest
That's amazing. I think I'm going to give Cramkey Dumps a try for my next exam. Thanks for telling me about them! CramKey admin please share more questions……You guys are amazing.
Nate Jul 12, 2025
I failed last week, I never know this site , but amazed to see all these questions were in my exam week before. I feel bad now, why I didn’t bother this site. Thanks Cramkey, Excellent Job.