| Exam Name: | PMI Agile Certified Practitioner (PMI-ACP) | ||
| Exam Code: | PMI-ACP Dumps | ||
| Vendor: | PMI | Certification: | PMI Agile |
| Questions: | 481 Q&A's | Shared By: | abdulrahman |
A project ' s Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.
What technique did the team use?
A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.
Which one of the following is the ideal option for the team to resolve this conflict?