Question 136

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities. How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Discussion
Sam
Can I get help from these dumps and their support team for preparing my exam?
Audrey Dec 15, 2025
Definitely, you won't regret it. They've helped so many people pass their exams and I'm sure they'll help you too. Good luck with your studies!
River
Hey, I used Cramkey Dumps to prepare for my recent exam and I passed it.
Lewis Dec 22, 2025
Yeah, I used these dumps too. And I have to say, I was really impressed with the results.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Dec 28, 2025
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Georgina
I used Cramkey Dumps to prepare for my recent exam and I have to say, they were a huge help.
Corey Dec 20, 2025
Really? How did they help you? I know these are the same questions appears in exam. I will give my try. But tell me if they also help in some training?
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Dec 25, 2025
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 137

What should the agile practitioner know about tracking velocity?

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Discussion
Question 138

While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)?

Options:

A.

How much risk is needed to develop an MMF

B.

How much money the organization will earn or save by having the MMF

C.

How many stakeholders are influencing the MMF

D.

How much time does an organization need to develop an MMF

Discussion
Question 139

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

Discussion