Question 72

An agile team is optimizing the workflow by investing in initiatives to identify and reduce unnecessary handovers and delays. What should the team do in this situation?

Options:

A.

Create a value stream map.

B.

Draw a risk burndown chart.

C.

Use a kanban board.

D.

Make a cumulative flow diagram.

Discussion
Question 73

A key stakeholder cannot attend the project vision statement development workshop. The stakeholder has emailed their requirements to the agile team lead, and believes that the vision statement is not critical.

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder's supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Discussion
Question 74

Questions 74

A project manager is working on a database migration project to cloud services (Refer to Migration Strategy to Cloud Services table). The project team has accumulated significant technical debt over several sprints due to pressure to deliver features quickly. This debt is nowimpacting their ability to deliver new features, leading to a notable decline in product performance and customer satisfaction.

Identify the actions the team should take to effectively manage technical debt while consistently delivering high-value features that align with stakeholder expectations.

Options:

A.

Form a separate learn dedicated lo handling technical debt, allowing the current team to focus on new features to maintain a competitive advantage and stakeholder satisfaction.

B.

Include technical debt tasks in every sprint, treating them with the same level of priority as new features, and continuously review the impact on the project's overall goals.

C.

Ignore the technical debt foe now and focus exclusively on delivering new features so that the project can maintain a competitive advantage and stakeholder satisfaction.

D.

Dedicate multiple consecutive sprints solely to addressing technical debt, halting new feature development temporarily to minimize the impact on the project's overall goals.

Discussion
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Jul 3, 2025
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Alaya
Best Dumps among other dumps providers. I like it so much because of their authenticity.
Kaiden Jul 23, 2025
That's great. I've used other dump providers in the past and they were often outdated or had incorrect information. This time I will try it.
Cecilia
Yes, I passed my certification exam using Cramkey Dumps.
Helena Jul 13, 2025
Great. Yes they are really effective
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Jul 19, 2025
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Question 75

A team member has made a mistake on a project. How should the scrum master address the mistake?

Options:

A.

Encourage all team members to follow existing processes.

B.

Require team members to complete a peer review of work and deliverables.

C.

Facilitate a retrospective to identity areas of improvement.

D.

Reward those who have the lowest occurrences of mistakes.