Question 140

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Discussion
Mylo
Excellent dumps with authentic information… I passed my exam with brilliant score.
Dominik Mar 14, 2026
That's amazing! I've been looking for good study material that will help me prepare for my upcoming certification exam. Now, I will try it.
Marley
Hey, I heard the good news. I passed the certification exam!
Jaxson Mar 25, 2026
Yes, I passed too! And I have to say, I couldn't have done it without Cramkey Dumps.
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Mar 21, 2026
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Addison
Want to tell everybody through this platform that I passed my exam with excellent score. All credit goes to Cramkey Exam Dumps.
Libby Mar 7, 2026
That's good to know. I might check it out for my next IT certification exam. Thanks for the info.
Question 141

A new team member asks what changes could accelerate a change to the project plan What should be the proper response?

Options:

A.

Competitors joined forces with the team

B.

The customer changed requirements

C.

Project team members obtained additional certifications

D.

Technology which did not interfere with the final product

Discussion
Question 142

During backlog refinement, a team routinely creates tests to demonstrate to the customer that each acceptance criterion has been met. Most acceptance tests results are observable or demonstrable, but testing for one requirement is providing a challenge to the team. The requirement states that the home button should be recognizable and the team is unsure how to test this.

What should the team lead do?

Options:

A.

Determine if the home button is present and if it is shaped like a house, it is recognizable.

B.

Record the product owner's opinion on how they will know if the button is recognizable.

C.

Skip creating a specific test for Ibis particular requirement because it is too abstract

D.

Consult the design team as subject matter experts (SMEs) for criteria on what makes a button recognizable.

Discussion
Question 143

Midway through an iteration an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

Options:

A.

Raise an impediment that resource tasks will be blocked and notify the product owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the scrum master to assign that team member's tasks to the next available resource

D.

Assume the team member's tasks to meet iteration goals and notify the product owner

Discussion