New Year Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-200 Exam Questions and Answers by sayed

Page: 20 / 35

PMI PMI-200 Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200 Dumps
Vendor: PMI Certification: PMI ACP
Questions: 482 Q&A's Shared By: sayed
Question 80

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?

Options:

A.

Holistically at the project level

B.

At the end of each sprint

C.

At a sprint level after each demo

D.

Periodically, at both the release and project level

Discussion
Nell
Are these dumps reliable?
Ernie Dec 16, 2025
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Aliza
I used these dumps for my recent certification exam and I can say with certainty that they're absolutely valid dumps. The questions were very similar to what came up in the actual exam.
Jakub Dec 3, 2025
That's great to hear. I am going to try them soon.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Dec 21, 2025
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Dec 6, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan Dec 16, 2025
That’s great!!! I’ll definitely give it a try. Thanks!!!
Question 81

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Discussion
Question 82

Questions 82

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Discussion
Question 83

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

Options:

A.

Reduce the scope of the release to meet the deadline.

B.

Deliver as many features as possible based on the new velocity.

C.

Extend the project timeline to accommodate the missing team member.

D.

Hire a new team member to replace the missing one.

Discussion
Page: 20 / 35
Title
Questions
Posted

PMI-200
PDF

$36.75  $104.99

PMI-200 Testing Engine

$43.75  $124.99

PMI-200 PDF + Testing Engine

$57.75  $164.99