Question 52

Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?

Options:

A.

The product owner may act as the stakeholders' proxy at the demo and that the stakeholders do not need to be directly involved with the team.

B.

The demo will show whether or not the team understands the level of effort required to complete the project.

C.

The stakeholders will learn whether or not the implementation has worked by getting immediate feedback so they can correct their assumptions for the next sprint.

D.

The stakeholders will be better positioned to evaluate whether or not the resources expended by the organization are worthwhile.

Discussion
Wyatt
Passed my exam… Thank you so much for your excellent Exam Dumps.
Arjun Jul 12, 2025
That sounds really useful. I'll definitely check it out.
Miriam
Highly recommended Dumps. 100% authentic and reliable. Passed my exam with wonderful score.
Milan Jul 17, 2025
I see. Thanks for the information. I'll definitely keep Cramkey in mind for my next exam.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Jul 17, 2025
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Teddie
yes, I passed my exam with wonderful score, Accurate and valid dumps.
Isla-Rose Jul 15, 2025
Absolutely! The questions in the dumps were almost identical to the ones that appeared in the actual exam. I was able to answer almost all of them correctly.
Question 53

A team member has asked a question about the responsibilities of the product manager, QA, and the team regarding quality. What should the agile project manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member's role may vary as stated in the definition of done (Do

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the product manager defines the functionality from end to end.

Discussion
Question 54

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Discussion
Question 55

Which option describes how risk should be managed in an agile project?

Options:

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stones they have been assigned

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.