Month End Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-200 Exam Questions and Answers by alia

Page: 11 / 35

PMI PMI-200 Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200 Dumps
Vendor: PMI Certification: PMI ACP
Questions: 482 Q&A's Shared By: alia
Question 44

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?

Options:

A.

Estimate and define the work items.

B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.

C.

Add features to the product backlog.

D.

Determine if the demand is or is not feasible.

Discussion
Question 45

During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

Options:

A.

Positively acknowledge the list and share it with management

B.

Immediately have the team implement the initiatives

C.

Help the team choose one or two initiatives for immediate implementation

D.

Ask the team to choose and implement the most complex initiative

Discussion
Question 46

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

Options:

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Discussion
Faye
Yayyyy. I passed my exam. I think all students give these dumps a try.
Emmeline Sep 12, 2024
Definitely! I have no doubt new students will find them to be just as helpful as I did.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Sep 21, 2024
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Alaia
These Dumps are amazing! I used them to study for my recent exam and I passed with flying colors. The information in the dumps is so valid and up-to-date. Thanks a lot!!!
Zofia Sep 9, 2024
That's great to hear! I've been struggling to find good study material for my exam. I will ty it for sure.
Esmae
I highly recommend Cramkey Dumps to anyone preparing for the certification exam.
Mollie Aug 15, 2024
Absolutely. They really make it easier to study and retain all the important information. I'm so glad I found Cramkey Dumps.
Question 47

A team developing application software is working in pairs. A project manager notices that important information is sometimes not shared among team members, leading to delays in the development process.

What should the project manager do to improve team performance and eliminate any communication impediments?

A For new pairs of developers based on the years of expertise and project management Knowledge

B. Use task boards so the team can keep track of the work done and future implementation planning.

C. Schedule in-person meetings at the end of each iteration, allowing team members to share knowledge and experience.

D. Seek expert judgment and a new collaboration model that will strengthen team cohesiveness.

Options:

Discussion
Page: 11 / 35
Title
Questions
Posted

PMI-200
PDF

$36.75  $104.99

PMI-200 Testing Engine

$43.75  $124.99

PMI-200 PDF + Testing Engine

$57.75  $164.99