Question 12

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Discussion
Annabel
I recently used them for my exam and I passed it with excellent score. I am impressed.
Amirah Feb 10, 2026
I passed too. The questions I saw in the actual exam were exactly the same as the ones in the Cramkey Dumps. I was able to answer the questions confidently because I had already seen and studied them.
Ace
No problem! I highly recommend Cramkey Dumps to anyone looking to pass their certification exams. They will help you feel confident and prepared on exam day. Good luck!
Harris Feb 3, 2026
That sounds amazing. I'll definitely check them out. Thanks for the recommendation!
Nylah
I've been looking for good study material for my upcoming certification exam. Need help.
Dolly Feb 15, 2026
Then you should definitely give Cramkey Dumps a try. They have a huge database of questions and answers, making it easy to study and prepare for the exam. And the best part is, you can be sure the information is accurate and relevant.
Peyton
Hey guys. Guess what? I passed my exam. Thanks a lot Cramkey, your provided information was relevant and reliable.
Coby Feb 16, 2026
Thanks for sharing your experience. I think I'll give Cramkey a try for my next exam.
Question 13

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

Options:

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Discussion
Question 14

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Discussion
Question 15

In a scrum team, who should be responsible for the budget and release plans?

Options:

A.

The scrum master assigns someone on the team to handle the budget, and the product owner is responsible for release plans

B.

The finance department is responsible for budget, and the product owner is responsible for release plans

C.

The scrum team as a whole, as they are self-organizing and share accountability

D.

The product owner is responsible for both the budget and the release plans

Discussion