Question 12

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Discussion
Fatima
Hey I passed my exam. The world needs to know about it. I have never seen real exam questions on any other exam preparation resource like I saw on Cramkey Dumps.
Niamh Mar 23, 2026
That's true. Cramkey Dumps are simply the best when it comes to preparing for the certification exam. They have all the key information you need and the questions are very similar to what you'll see on the actual exam.
Rae
I tried using Cramkey dumps for my recent certification exam and I found them to be more accurate and up-to-date compared to other dumps I've seen. Passed the exam with wonderful score.
Rayyan Mar 14, 2026
I see your point. Thanks for sharing your thoughts. I might give it a try for my next certification exam.
Robin
Cramkey is highly recommended.
Jonah Mar 22, 2026
Definitely. If you're looking for a reliable and effective study resource, look no further than Cramkey Dumps. They're simply wonderful!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Mar 28, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Question 13

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

Options:

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Discussion
Question 14

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Discussion
Question 15

In a scrum team, who should be responsible for the budget and release plans?

Options:

A.

The scrum master assigns someone on the team to handle the budget, and the product owner is responsible for release plans

B.

The finance department is responsible for budget, and the product owner is responsible for release plans

C.

The scrum team as a whole, as they are self-organizing and share accountability

D.

The product owner is responsible for both the budget and the release plans

Discussion