Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-200 Exam Questions and Answers by keyaan

Page: 31 / 35

PMI PMI-200 Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200 Dumps
Vendor: PMI Certification: PMI ACP
Questions: 482 Q&A's Shared By: keyaan
Question 124

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

Options:

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Discussion
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Aug 10, 2026
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Aug 5, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Inaya
Passed the exam. questions are valid. The customer support is top-notch. They were quick to respond to any questions I had and provided me with all the information I needed.
Cillian Aug 25, 2026
That's a big plus. I've used other dump providers in the past and the customer support was often lacking.
Ilyas
Definitely. I felt much more confident and prepared because of the Cramkey Dumps. I was able to answer most of the questions with ease and I think that helped me to score well on the exam.
Saoirse Aug 9, 2026
That's amazing. I'm glad you found something that worked for you. Maybe I should try them out for my next exam.
Victoria
Hey, guess what? I passed the certification exam! I couldn't have done it without Cramkey Dumps.
Isabel Aug 17, 2026
Same here! I was so surprised when I saw that almost all the questions on the exam were exactly what I found in their study materials.
Question 125

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Discussion
Question 126

How can a project team effectively work toward a common goal and communicate as they scale and expand to build a new business-critical platform, given that they have been responsible for a small customer-facing product with little complexity over the past 2 years?

Options:

A.

Daily coordination meeting

B.

Instant messaging tools

C.

Web conferencing

D.

Work collaboration platform

Discussion
Question 127

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release.

What should the agile coach do?

Options:

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Discussion
Page: 31 / 35
Title
Questions
Posted

PMI-200
PDF

$36.75  $104.99

PMI-200 Testing Engine

$43.75  $124.99

PMI-200 PDF + Testing Engine

$57.75  $164.99