Pre-Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: get65

PMI Updated PMI-200 Exam Questions and Answers by zayne

Page: 5 / 35

PMI PMI-200 Exam Overview :

Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200 Dumps
Vendor: PMI Certification: PMI ACP
Questions: 482 Q&A's Shared By: zayne
Question 20

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

Options:

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Discussion
Question 21

Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.

What should the project manager do?

Options:

A.

Mention the risks during the daily standups and ensure all agreed-upon response actions are discussed by the team.

B.

Remind the learn daily about the threats and request a response regarding which risks have been identified and resolved

C.

Arrange weekly meetings and invite the project sponsor to discuss the importance of the project with the team.

D.

Create a space on the board to prioritize the threats, along with an update on the actions that are in progress and what still needs to be done.

Discussion
Question 22

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals needs to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Discussion
Elise
I've heard that Cramkey is one of the best websites for exam dumps. They have a high passing rate and the questions are always up-to-date. Is it true?
Cian Apr 9, 2026
Definitely. The dumps are constantly updated to reflect the latest changes in the certification exams. And I also appreciate how they provide explanations for the answers, so I could understand the reasoning behind each question.
Osian
Dumps are fantastic! I recently passed my certification exam using these dumps and I must say, they are 100% valid.
Azaan Apr 12, 2026
They are incredibly accurate and valid. I felt confident going into my exam because the dumps covered all the important topics and the questions were very similar to what I saw on the actual exam. The team of experts behind Cramkey Dumps make sure the information is relevant and up-to-date.
Billy
It was like deja vu! I was confident going into the exam because I had already seen those questions before.
Vincent Apr 10, 2026
Definitely. And the best part is, I passed! I feel like all that hard work and preparation paid off. Cramkey is the best resource for all students!!!
Lois
I passed my exam with wonderful score. Their dumps are 100% valid and I felt confident during the exam.
Ernie Apr 23, 2026
Absolutely. The best part is, the answers in the dumps were correct. So, I felt confident and well-prepared for the exam.
Anaya
I found so many of the same questions on the real exam that I had already seen in the Cramkey Dumps. Thank you so much for making exam so easy for me. I passed it successfully!!!
Nina Apr 11, 2026
It's true! I felt so much more confident going into the exam because I had already seen and understood the questions.
Question 23

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Discussion
Page: 5 / 35
Title
Questions
Posted

PMI-200
PDF

$36.75  $104.99

PMI-200 Testing Engine

$43.75  $124.99

PMI-200 PDF + Testing Engine

$57.75  $164.99