B is the correct answer. four parts of the communications model are Sender, Message, Medium, and Receiver
Question 65
Which of the following is part of the expectancy theory of motivation?
Options:
A.
Clear, specific, and challenging goals generally motivate team members
B.
Project managers should ensure that tasks assigned to project participants match their skills and the organizational climate is conducive to helping them meet their needs and achieving a sense
of competence
C.
People tend to be highly productive and motivated if they believe their efforts will lead to successful results and that success will lead to personal rewards
B is the correct answer. All statements are true EXCEPT B
Walter
Yayyy!!! I passed my exam with the help of Cramkey Dumps. Highly appreciated!!!!
Angus(not set)
YES….. I saw the same questions in the exam.
Mariam
Do anyone think Cramkey questions can help improve exam scores?
Katie(not set)
Absolutely! Many people have reported improved scores after using Cramkey Dumps, and there are also success stories of people passing exams on the first try. I already passed this exam. I confirmed above questions were in exam.
Nell
Are these dumps reliable?
Ernie(not set)
Yes, very much so. Cramkey Dumps are created by experienced and certified professionals who have gone through the exams themselves. They understand the importance of providing accurate and relevant information to help you succeed.
Madeleine
Passed my exam with my dream score…. Guys do give these dumps a try. They are authentic.
Ziggy(not set)
That's really impressive. I think I might give Cramkey Dumps a try for my next certification exam.
Miley
Hey, I tried Cramkey Dumps for my IT certification exam. They are really awesome and helped me pass my exam with wonderful score.
Megan(not set)
That’s great!!! I’ll definitely give it a try. Thanks!!!
Question 67
When should the project expeditor form of organization be used?
Options:
A.
When the project is extremely important to the organization
B.
When a project's cost and importance are relatively low
C.
When the project manager has a lot of responsibility and accountability
D.
When the organization's primary source of revenue is derived from projects